Empennage [127.5 Hours]
Horizontal Stabilizer [40.5 Hours]
| [8 Nov 2010] |
[3 Hours] - Broke stiffener edges and drilled them to the spar |
| [9 Nov 2010] |
[2.5 Hours] - Drilled hinge brackets and riveted center bearing |
| [10 Nov 2010] |
[4 Hours] - Tapered and bent HS front spar reinforcement |
| [11 Nov 2010] |
[5.5 Hours] - Assembled, drilled and deburred left HS |
| [12 Nov 2010] |
[9 Hours] - Assembled, drilled and deburred right HS, dimpled parts |
| [13 Nov 2010] |
[7 Hours] - Primed parts, dimpled skin, started riveting left HS |
| [14 Nov 2010] |
[5.5 Hours] - Dimpled skin, riveted left HS, started right HS |
| [15 Nov 2010] |
[4 Hours] - Finished the horizontal stabilizer! |
Vertical Stabilizer [10.5 Hours]
| [17 Nov 2010] |
[2 Hours] - Started VS, drilled skeleton and skin |
| [18 Nov 2010] |
[2.5 Hours] - Drilled VS, deburred and dimpled parts |
| [19 Nov 2010] |
[6 Hours] - Primed VS ribs, riveted/finished VS |
Rudder [19.5 Hours]
| [20 Nov 2010] |
[6 Hours] - Cut/drilled stiffeners, deburring |
| [21 Nov 2010] |
[2.5 Hours] - Primed and riveted stiffeners |
| [29 Nov 2010] |
[4 Hours] - Drilled, deburred, dimpled rudder skeleton |
| [1 Dec 2010] |
[5 Hours] - Primed skeleton and riveted rudder |
| [2 Dec 2010] |
[2 Hours] - Finished rudder leading edge. Rudder complete! |
Elevators [48.5 Hours]
| [3 Dec 2010] |
[3 Hours] - Cut and smoothed the elevator stiffeners |
| [5 Dec 2010] |
[3 Hours] - Drilled, deburred, dimpled, primed right elevator stiffeners and skin |
| [6 Dec 2010] |
[1 Hour] - Back riveted right elevator stiffeners |
| [6 Jan 2011] |
[4 Hours] - Clecoed elevator counterweight assemblies |
| [13 Jan 2011] |
[2.5 Hours] - Bent trailing edge, match drilled elevator |
| [27 Jan 2011] |
[2 Hours] - Primed, dimpled, deburred parts, riveted skeleton |
| [28 Jan 2011] |
[2 Hours] - Filed right elevator counterweight |
| [29 Jan 2011] |
[2.5 Hours] - Riveted right elevator |
| [24 Feb 2011] |
[2 Hours] - Rolled leading edge, finished right elevator |
| [23 Mar 2011] |
[4 Hours] - Left elevator stiffeners |
| [25 Mar 2011] |
[1 Hour] - Drilled left counterweight |
| [29 Mar 2011] |
[4.5 Hours] - Riveted trim stiffener, bent trailing edge, drilled, deburred |
| [30 Mar 2011] |
[2.5 Hours] - Deburred, countersink, dimpled, primed parts |
| [1 Apr 2011] |
[2 Hours] - Made elevator riblet |
| [5 Apr 2011] |
[3.5 Hours] - Riveted left elevator skeleton, made trim servo bracket |
| [6 Apr 2011] |
[2.5 Hours] - Dimpled and riveted left elevator |
| [22 May 2011] |
[1.5 Hours] - Started rolling left elevator leading edge |
| [23 May 2011] |
[1 Hour] - Finished rolling/riveting leading edge |
| [8 Jun 2011] |
[4 Hours] - Attached elevators to HS |
Trim Tab [8.5 Hours]
| [7 Apr 2011] |
[3 Hours] - Cut off trim tab tabs, drilled trim tab |
| [8 Apr 2011] |
[1.5 Hours] - Dimpled and started riveting trim tab |
| [13 Apr 2011] |
[2 Hours] - Riveted trim tab and hinges |
| [15 May 2011] |
[2 Hours] - Made and installed riblets |
|